NUCLEAR ENERGY

Why is India so keen on importing US nuclear reactors that even the US doesn't seem to want?

The deals have more to do with the financial well-being of US equipment suppliers than with the aspirations of India's electricity consumers.

A report by the Institute for Energy Economics and Financial Analysis, an independent organisation in the US, has warned that India’s plans to import 12 nuclear reactors from ailing American equipment suppliers is financially fraught and irrelevant for India’s electricity needs.

The release of the report titled “Bad Choice: The Risks, Costs and Viability of US Nuclear Reactors in India” on Wednesday coincides with Prime Minister Narendra Modi’s visit to Washington to attend the Nuclear Security Summit.

The proposals for six Westinghouse Electric’s AP1000 reactors in Mithi Virdi, Gujarat, and the same number of GE-Hitachi’s Economic Simplified Boiling Water Reactor in Kovvada, Andhra Pradesh, are part of the Indian government’s return gift for Washington’s cooperation in concluding the Indo-US nuclear deal.

Matters of relevance

In January, Westinghouse had expressed hope of a significant announcement by Modi during his US visit. But that does not seem to have materialised. On March 30, Westinghouse Electric’s CEO Daniel Roderick told Reuters that he expected a deal to be signed in June. According to the article:

"He [Roderick] declined to say how much the deal would be worth, or the price per unit of electricity, but said India had judged Westinghouse to be a 'competitive energy source provider' and this would allow the contract to go on to the next phase."

If the institute's report is anything to go by, none of the 12 reactors proposed to be built by American suppliers will be competitive in terms of capital costs or electricity rates. In fact, the report even throws into doubt the relevance of the reactors as an energy source to reckon with in the near to mid-term.

If built, the 12 reactors will cost between Rs 6.3 lakh crore ($95 billion) and Rs 11 lakh crore ($170 billion). That will translate to unaffordable and obscenely high electricity tariffs. Levelised tariffs for the Kovvada project are expected to range from Rs 15.85 to Rs 26.04 per kilowatt-hour, for a project start date of 2032. The corresponding numbers for the Mithi Virdi reactor are between Rs 9.05 and Rs 17.75 per kWh. Contrast this with the steeply falling prices of solar electricity, which are expected to hover around Rs 3 per kWh in 2032.

Sole guinea pig

The wide range in capital and electricity costs reflects the uncertainties associated with any nuclear project, but particularly with the AP 1000 and ESBWR designs. The report notes that there are no reactors of either design currently operational anywhere in the world. AP1000 reactors are currently under construction in the US and China. In both locations, the reactors have suffered immense cost and time overruns.

GE’s ESBWR design has never been built. India will be the first and only guinea pig till date. Significantly, GE has declared that it is unwilling to risk building this untested design unless India clarifies its stance on indemnifying the equipment supplier from the financial consequences in the event of an accident.

However, reports indicate that Westinghouse is chomping at the bit to get going with the Gujarat project, where it hopes to supply six AP1000 units of 1,150 megawatts each. It has indicated an interest in Kovvada as well in case of a GE pullout. Westinghouse’s eagerness is understandable. Its losses have dragged its parent Toshiba into a massive controversy. The Japanese conglomerate admitted last November that its US-based subsidiary Westinghouse had incurred massive losses owing to delays in new plant constructions and cost overruns in the years after the Fukushima nuclear disaster.

While Prime Minister Narendra Modi is desperately wooing Westinghouse for a nuclear park in his home state, Toshiba is reportedly under investigation in the US for financial irregularities arising from its subsidiary’s losses.

Unviable projects

The deals that the Indian government is bending backwards to stitch up have more to do with the financial well-being of US equipment suppliers than with the aspirations of India’s electricity consumers or taxpayers. The numbers in the institute’s report suggest that unless the projects are heavily subsidised by taxpayers, electricity from the reactors proposed at Kovvada and Mithi Virdi will be too expensive for consumers to purchase. Apart from the nuclear risks, just the day-to-day operations of these plants will result in a financial and economic disaster for utilities, ratepayers and taxpayers.

The first new reactors in Mithi Virdi and Kovvada will take 11 to 15 years to build, assuming the projects manage to avoid likely delays. No electricity from the new reactors at Mithi Virdi and Kovvada should be expected until sometime between 2029 and 2032. This is the best-case scenario assuming construction starts in 2017.

But this is unrealistic. Land acquisition – a politically fraught process – has not even commenced at the two sites. Indian farmers do not part easily with their land. Any delay in land acquisition will further increase capital costs. Consequently, tariff rates will be even higher than what is estimated by the institute's analysts.

The report warns that:


“cost and schedule uncertainties associated with the Mithi Virdi and Kovvada projects will likely be even more pronounced if the Government of India pushes ahead with its Make in India program with respect to procurement of specialised components and/or erection and commissioning of the plants.”  

An important reason for time and cost overruns in Westinghouse’s Chinese and US installations is the difficulty that vendors in the United States are having in meeting the design and quality specifications of the first-of-its-kind AP1000 model.

In the past, the Indian government has sought to thwart legitimate concerns about its opaque pursuits in nuclear projects by hinting at a foreign hand. Curiously, in this instance, the Institute for Energy Economics and Financial Analysis, the foreign hand that is questioning the viability of the reactor imports is American – just like the equipment suppliers that stand to make a quick buck at the cost of the Indian public. In fact, the author of the report, David Schlissel, has spent 40 years following the US nuclear industry.

That then leaves observers wondering why the Indian government is hell-bent on importing American nuclear reactors that even the Americans don’t seem to want. One thing is clear, though: financing these expensive US reactors will divert much-needed money from India’s planned commitments in renewable resources and energy efficiency to GE and Westinghouse’s American and Japanese shareholders.

Nityanand Jayaraman is a writer and activist from Chennai associated with the National Alliance of Anti-Nuclear Movements.

We welcome your comments at letters@scroll.in.
Sponsored Content  BY 

Harvard Business School’s HBX brings the future of business education to India with online programs

HBX is not only offering courses online, but also connecting students to the power of its network.

The classic design of the physical Harvard Business School (HBS) classroom was once a big innovation – precisely designed teaching amphitheaters laid out for every student to participate from his or her seat with a “pit” in the center of the room from which professors orchestrate discussions analyzing business cases like a symphony lead. When it came to designing the online experience of HBX—the school’s digital learning initiative—HBS faculty worked tirelessly to blend these tenets of the HBS classroom pedagogy with the power of new technology. With real-world problem solving, active learning, and social learning as its foundation, HBX offers immersive and challenging self-paced learning experiences through its interactive online learning platform.

Reimagining digital education, breaking the virtual learning mold

Typically, online courses follow a one-way broadcast mode – lectures are video recorded and reading material is shared – and students learn alone and are individually tested. Moving away from the passive learning model, HBX has developed an online platform that leverages the HBS ‘case-based pedagogy’ and audio-visual and interaction tools to make learning engaging.

HBX courses are rarely taught through theory. Instead, students learn through real-world problem-solving. Students start by grappling with a business problem – with real world data and the complexity in which a business leader would have to make a decision – and learn the theory inductively. Thus even as mathematical theories are applied to business situations, students come away with a greater sense of clarity and perspective, whether it is reading a financial report, understanding why a brand’s approach to a random sample population study may or may not work, or how pricing works.

HBX Platform | Courses offered in the HBX CORe program
HBX Platform | Courses offered in the HBX CORe program

“Learning about concepts through real-life cases was my favorite part of the program. The cases really helped transform abstract concepts into observable situations one could learn from. Furthermore, it really helped me understand how to identify situations in which I could use the tools that HBX equipped me with,” says Anindita Ravikumar, a past HBX participant. India’s premier B-school IIM-Ahmedabad has borrowed the very same pedagogy from Harvard. Learning in this manner is far more engaging, relatable, and memorable.

Most lessons start with a short 2-3 minute video of a manager talking about the business problem at hand. Students are then asked to respond on how they would handle the issue. Questions can be in the form of either a poll or reflections. Everyone’s answers are then visible to the ‘classroom’. In the words of Professor Bharat Anand, Faculty Chair, HBX, “This turns out to be a really important distinction. The answers are being updated in real-time. You can see the distribution of answers, but you can also see what any other individual has answered, which means that you’re not anonymous.” Students have real profiles and get to know their ‘classmates’ and learn from each other.

HBX Interface | Students can view profiles of other students in their cohort
HBX Interface | Students can view profiles of other students in their cohort

Professor Anand also says, “We have what we call the three-minute rule. Roughly every three minutes, you are doing something different on the platform. Everyone is on the edge of their seats. Anyone could be called on to participate at any time. It’s a very lean forward mode of learning”. Students get ‘cold-called’ – a concept borrowed from the classroom – where every now and then individuals will be unexpectedly prompted to answer a question on the platform and their response will be shared with other members of the cohort. It keeps students engaged and encourages preparedness. While HBX courses are self-paced, participants are encouraged to get through a certain amount of content each week, which helps keep the cohort together and enables the social elements of the learning experience.

More than digital learning

The HBS campus experience is valued by alumni not just for the academic experience but also for the diverse network of peers they meet. HBX programs similarly encourage student interactions and opportunities for in-person networking. All HBXers who successfully complete their programs and are awarded a credential or certificate from HBX and Harvard Business School are invited to the annual on-campus HBX ConneXt event to meet peers from around the world, hear from faculty and business executives, and also experience the HBS campus near Cambridge.

HBXers at ConneXt, with Prof. Bharat Anand
HBXers at ConneXt, with Prof. Bharat Anand

Programs offered today

HBX offers a range of programs that appeal to different audiences.

To help college students and recent graduates prepare for the business world, HBX CORe (Credential of Readiness) integrates business essentials such as analytics, economics, and financial accounting. HBX CORe is also great for those interested in an MBA looking to strengthen their application and brush up their skills to be prepared for day one. For working professionals, HBX CORe and additional courses like Disruptive Strategy, Leading with Finance, and Negotiation Mastery, can help deepen understanding of essential business concepts in order to add value to their organizations and advance their careers.

Course durations range from 6 to 17 weeks depending on the program. All interested candidates must submit a free, 10-15 minute application that is reviewed by the HBX admissions team by the deadlines noted on the HBX website.

For more information, please review the HBX website.

This article was produced by the Scroll marketing team on behalf of HBX and not by the Scroll editorial team.